Jun 17, 2009 13:11 JST

Source: M+W Group

M+W Zander Completes Factory to Manufacture Solar Cells for Q-Cells in Malaysia; 500 Megawatt Annual Output

Stuttgart, Germany, Jun 17, 2009 - (ACN Newswire) - Engineering company M+W Zander has designed and built a new solar cell manufacturing facility for Q-Cells in Malaysia, and has handed over the facility on schedule. This major project was completed within a tight construction time frame of less than 8 months to achieve Ready for Equipment. The three-storey solar-cell factory with eight production lines has an annual output of 500 megawatts (peak).

This major order encompassed the complete value chain from site master planning, detailed design through to procurement and construction management followed by hook-up of all process equipment. In addition to the site master planning M+W Zander was also responsible for design and co-ordination of the process media systems within the newly developed science park.

A multi-national team of highly motivated M+W Zander engineers from Germany and Malaysia began work for the site master plan in February 2008. Completion of site backfill, allowed for the 1st piling on 15th May last year. Successfully achieving "Ready for Equipment" by 31st December 2008.

"Thanks to the close collaboration of our teams within M+W Zander Group we could accelerate the project enourmously to meet the challenging timeframe," said Martin Beigl and Helmut Kurzboeck, Managing Directors of M+W Zander in Germany and Asia.

Contact:
Michael Gemeinhardt
Phone: +49 711 8804-1420
Email: michael.gemeinhardt@mw-zander.com 
Source: M+W Group
Sectors: Daily News

Copyright ©2025 ACN Newswire. All rights reserved. A division of Asia Corporate News Network.


Latest Release

More Latest Release >>