Hitachi Announces Suspension of UK Nuclear Power Stations Construction Project and Posting of Impairment Loss and Related Expenses
On Consolidated Basis, Posting of Extraordinary Loss on Unconsolidated Basis, and Revisions to Full-year Consolidated Business Forecast
TOKYO, Jan 17, 2019 - (JCN Newswire) - Hitachi, Ltd. (TSE: 6501) today announced that it has decided to suspend its new nuclear power stations project in the UK (Horizon Project) that Horizon Nuclear Power Limited (HNP), a subsidiary of Hitachi and power generation development company in the UK, has been undertaking at Wylfa Newydd on Anglesey Island in north-west Wales. The decision was made from the viewpoint of Hitachi?s economic rationality as a private enterprise.
| Revisions of Business Forecast |
Accordingly, Hitachi plans to post an impairment loss and other expenses on consolidated financial results for fiscal 2018, the year ending March 31, 2019 (from April 1, 2018 to March 31, 2019). It also plans to post an extraordinary loss on unconsolidated financial results for fiscal 2018, the year ending March 31, 2019. Based on these points, Hitachi has revised its full-year consolidated business forecast for fiscal 2018, the year ending March 31, 2019 as follows.
1. Posting Losses Associated with the Suspension of the Horizon Project
(1) Backgrounds and Contents of the Losses
Hitachi acquired HNP from the UK subsidiaries of the two German power companies for 88.9 billion yen (697 million pounds) in November 2012 to develop its nuclear business in the UK and to contribute to the UK Government's energy policy, and to maintain and reinforce the business base that supports the Japanese nuclear industry. Based on an Advanced Boiling Water Reactor (ABWR(1)), which is a "Generation III+" reactor with an extensive construction and operation track record in Japan, Hitachi has worked on developing a nuclear power plant in order to build two UK ABWR units adapted to UK requirements.
Hitachi has held detailed discussions with the UK Government over various options about how the UK Government might support the project including potential for equity and debt investments. The parties, with the cooperation of the Japanese Government, have held discussions in good faith in regard to the financial structure for the project and various conditions for the building and operation of the nuclear power station.
Since the acquisition of HNP, Hitachi has set the following three points as the main criteria for business continuation and reviewed the Horizon Project from the viewpoint of its economic rationality: (1) securing reasonable returns as a private enterprise, (2) realizing a financial structure on the premise of making Horizon Project off balance sheet, (3) limiting an investment amount to an acceptable range as a private enterprise.
Unfortunately, despite the best efforts of everyone involved the parties have not been able to reach an agreement to the satisfaction of all concerned. As a result, Hitachi has decided to suspend the project at this time from the viewpoint of its economic rationality as a private enterprise, as it is now clear that further time is needed to develop a financial structure for the Horizon Project and the conditions for building and operating the nuclear power stations.
Consequently, Hitachi plans to post an impairment loss and related expenses of approximately 300.0 billion yen as other expenses on consolidated financial results for fiscal 2018, the year ending March 31, 2019 (from April 1, 2018 to March 31, 2019). It also plans to post losses of approximately 300.0 billion yen associated with the suspension of the nuclear power plant construction project in the UK as extraordinary losses on unconsolidated financial results for fiscal 2018, the year ending March 31, 2019. These amounts are current estimates, and will be settled in its consolidated and unconsolidated financial results for fiscal 2018, the year ending March 31, 2019.
(2) Nuclear Energy Business in the Future
To further contribute to UK energy policy, Hitachi will continue to discuss a nuclear power program with the UK Government. Also going forward, considering that Hitachi has the global head office function for its Railway Systems business, the rolling stock manufacturing base, and the base for research and development of cutting-edge digital solutions in the UK, Hitachi will maintain its contribution to the UK economy, further technology development, and improvement of QoL(2) in the UK through its Social Innovation Business.
In Japan, Hitachi will be steadily engaged in the restarting of domestic nuclear power plants and the decommissioning of Fukushima Daiichi Nuclear Power Station for the foreseeable future. Furthermore, Hitachi will continue to develop businesses that make use of its strengths with strong reliability and expertise, such as solutions to support improvements in availability of power plants and extension of plant life.
2. Revisions of Business Forecast
a. Revisions of Full-year Consolidated Business Forecast for Fiscal 2018 (From April 1, 2018 to March 31, 2019) http://www.acnnewswire.com/topimg/Low_HitachiRevisionsBusinessForecast.jpg
b. Reasons for Revisions The impairment loss of approximately 300.0 billion yen will be posted as other expenses due to the suspension of the Horizon Project. As a result, Hitachi has revised its forecasts for consolidated financial results for fiscal 2018, the year ending March 31, 2019, which were announced on October 26, 2018, as indicated above.
(1) Advanced Boiling Water Reactor (2) Quality of Life
Contact:Hitachi Ltd
Corporate Communications
Tel: +81-3-3258-1111
Source: Hitachi, Ltd. Sectors: Energy, Alternatives
Copyright ©2024 JCN Newswire. All rights reserved. A division of Japan Corporate News Network.
|
Latest Release
JCB enables JCB Contactless acceptance at Taichung MRT in Taiwan Apr 26, 2024 10:00 JST
| Mazda Production and Sales Results for March 2024 and for April 2023 through March 2024 Apr 25, 2024 18:21 JST
| MHI Begins Operation of SOEC Test Module the Next-Generation High-Efficiency Hydrogen Production Technology at Takasago Hydrogen Park Apr 25, 2024 17:45 JST
| GAC Honda to Begin Sales of All-new e:NP2, the Second Model of e:N Series Apr 25, 2024 16:50 JST
| Toyota Exhibiting at Beijing Motor Show 2024 Apr 25, 2024 16:25 JST
| Honda Reaches Basic Agreement with Asahi Kasei on Collaboration for Production of Battery Separators for Automotive Batteries in Canada Apr 25, 2024 11:10 JST
| UNIQLO Sponsors KAWS + Warhol Exhibition Tour, Starting in Pittsburgh Apr 25, 2024 09:00 JST
| Mitsubishi Power Begins Commercial Operation of Seventh M701JAC Gas Turbine in Thailand GTCC Project; Achieves 75,000 AOH To-Date Apr 24, 2024 17:19 JST
| MC and Denka Sign J/V Agreement in Fullerene Business Apr 24, 2024 17:02 JST
| Mitsubishi Motors Posts Record Sales in the Philippines in FY2023 Apr 24, 2024 13:56 JST
| NEC Develops High-speed Generative AI Large Language Models (LLM) with World-class Performance Apr 24, 2024 13:25 JST
| Fujitsu SX Survey reveals key success factors for sustainability Apr 23, 2024 10:25 JST
| Fujitsu and METRON collaborate to drive ESG success: slashing energy costs, boosting productivity with new manufacturing industry solutions Apr 22, 2024 16:09 JST
| NEC Strengthens Commitment to Space Industry with Investment in Seraphim Space Venture Fund II Apr 22, 2024 15:09 JST
| Soft Space Launches the First and Only JCB Payment Gateway in Malaysia Apr 22, 2024 15:00 JST
| TOYOTA GAZOO Racing takes a one-two in Croatian thriller Apr 22, 2024 10:47 JST
| First-ever Mazda CX-80 Crossover SUV Unveiled in Europe Apr 19, 2024 13:50 JST
| Fujitsu develops technology to convert corporate digital identity credentials, enabling participation of non-European companies in European data spaces Apr 19, 2024 10:17 JST
| Mitsubishi Heavy Industries and NGK to Jointly Develop Hydrogen Purification System from Ammonia Cracking Gas Apr 18, 2024 17:01 JST
| Toyota Launches All-New Land Cruiser "250" Series in Japan Apr 18, 2024 13:39 JST
|
More Latest Release >>
|